Forecast Resources Across Projects
|
|
|
|
|
==================================
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
Allocate the needed time for specific tasks under a planned shift. Once that is done, analyse Key
|
|
|
|
|
Performance Indicators (KPIs), so you can evaluate your employees’ performance and workload, besides
|
|
|
|
|
the progress of your projects/tasks when comparing the planned and effective hours.
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
Allocate times under shifts
|
|
|
|
|
===========================
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
When planning a shift, in the *Planning* application, create a project and a task on the fly,
|
|
|
|
|
or simply select the one you want.
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
.. image:: media/allocate_time.png
|
|
|
|
|
:align: center
|
|
|
|
|
:alt: Planning form to choose the project, task and allocated hours in Odoo Planning
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
| *Allocated Time (%)* allows you to define the percentage of time you would like your employee to
|
|
|
|
|
work on that specific task during his shift. See that information in hours on *Allocated hours*.
|
|
|
|
|
| The calculation shows you how many hours out of the total shift time (*End date* - *Start date*)
|
|
|
|
|
are spent by the employee on that task.
|
|
|
|
|
| On :menuselection:`Project --> Planning --> By Project`, immediately see the total number of
|
|
|
|
|
employees allocated per project.
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
.. image:: media/planning_project.png
|
|
|
|
|
:align: center
|
|
|
|
|
:alt: Planning by project view in Odoo Project
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
Compare forecast hours with the effective ones
|
|
|
|
|
==============================================
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
Now, once the employee has timesheeted his hours in the task, go to *Project* and with the
|
|
|
|
|
*View list*, under *All Tasks*, conveniently see the *Planned Hours* compared to the
|
|
|
|
|
*Remaining Hours*, and a calculation of the *Progress*.
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
.. image:: media/compare_forecast.png
|
|
|
|
|
:align: center
|
|
|
|
|
:alt: View of all tasks and their planned and remaining hours in Odoo Project
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
.. important::
|
|
|
|
|
Reminder: the option *Timesheets* has to be enabled on your project.
|
2016-03-03 20:32:13 +07:00
|
|
|
|
|
2020-03-20 20:00:14 +07:00
|
|
|
|
.. image:: media/enable_timesheets.png
|
|
|
|
|
:align: center
|
|
|
|
|
:height: 400
|
|
|
|
|
:alt: Under the settings of a project enable timesheets in Odoo Project
|