[ADD] Manufacturing: OEE
closes odoo/documentation#10288
X-original-commit: 63ba53a942
Signed-off-by: John Holton (hojo) <hojo@odoo.com>
This commit is contained in:
parent
6aaefcd2b8
commit
341aa8e4be
@ -16,3 +16,4 @@ Workflows
|
|||||||
workflows/byproducts
|
workflows/byproducts
|
||||||
workflows/allocation
|
workflows/allocation
|
||||||
workflows/continuous_improvement
|
workflows/continuous_improvement
|
||||||
|
workflows/oee
|
||||||
|
@ -0,0 +1,169 @@
|
|||||||
|
===============================
|
||||||
|
Overall equipment effectiveness
|
||||||
|
===============================
|
||||||
|
|
||||||
|
.. |MO| replace:: :abbr:`MO (manufacturing order)`
|
||||||
|
.. |OEE| replace:: :abbr:`OEE (overall equipment effectiveness)`
|
||||||
|
.. |BoM| replace:: :abbr:`BoM (Bill of Materials)`
|
||||||
|
|
||||||
|
In Odoo's *Manufacturing* app, *overall equipment effectiveness* (OEE) represents the amount of time
|
||||||
|
a work center is fully productive. |OEE| is displayed as a percentage of the total time a work
|
||||||
|
center is active.
|
||||||
|
|
||||||
|
Fully productive time is considered to be time when the work center is operational **and**
|
||||||
|
processing work orders that have not exceeded their *expected duration*.
|
||||||
|
|
||||||
|
|OEE| helps manufacturing teams understand the efficiency of work centers, and the causes of
|
||||||
|
manufacturing downtime.
|
||||||
|
|
||||||
|
.. important::
|
||||||
|
Since |OEE| tracks work center productivity, using it requires enabling the work centers feature
|
||||||
|
in the settings of the Manufacturing app.
|
||||||
|
|
||||||
|
To do so, navigate to :menuselection:`Manufacturing app --> Configuration --> Settings`, and tick
|
||||||
|
the checkbox next to :guilabel:`Work Orders`, under the :guilabel:`Operations` heading. Then,
|
||||||
|
click :guilabel:`Save`.
|
||||||
|
|
||||||
|
Efficiency standards
|
||||||
|
====================
|
||||||
|
|
||||||
|
For |OEE| to accurately reflect the percentage of fully productive time for a work center, the work
|
||||||
|
center **must** be properly configured with the correct productivity metrics. These include the work
|
||||||
|
center's *time efficiency*, *capacity*, and *OEE target*.
|
||||||
|
|
||||||
|
Time efficiency
|
||||||
|
---------------
|
||||||
|
|
||||||
|
Time efficiency represents the efficiency of a work center when processing work orders, and is
|
||||||
|
represented as a percentage. A time efficiency value of 100% signifies that the work center
|
||||||
|
processes work orders at the speed of the expected duration, as listed on a product's |BoM|. A value
|
||||||
|
less than or greater than 100% signifies that the work center processes work orders slower or faster
|
||||||
|
than an operation's expected duration, respectively.
|
||||||
|
|
||||||
|
To set the time efficiency for a work center, navigate to :menuselection:`Manufacturing app -->
|
||||||
|
Configuration --> Work Centers`, and select a work center. On the :guilabel:`General Information`
|
||||||
|
tab, enter a numerical value in the :guilabel:`Time Efficiency` field.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
Manufacturing a *chair* product requires two operations: *cut* and *assemble*. The product's
|
||||||
|
|BoM| lists an expected duration of 30 minutes for each operation.
|
||||||
|
|
||||||
|
The cut operation is carried out at the *cut station* work center, which has a time efficiency
|
||||||
|
value of 50%. This means it takes twice as long to complete the operation, for a total time of
|
||||||
|
one hour.
|
||||||
|
|
||||||
|
The assemble operation is carried out at the *assembly line* work center, which has a time
|
||||||
|
efficiency value of 200%. This means it takes half as long to complete the operation, for a total
|
||||||
|
time of 15 minutes.
|
||||||
|
|
||||||
|
Capacity
|
||||||
|
--------
|
||||||
|
|
||||||
|
Capacity represents how many units of a product can be produced in parallel at a work center. The
|
||||||
|
duration of work orders for multiple units increases or decreases, based on how many units the work
|
||||||
|
center can handle.
|
||||||
|
|
||||||
|
To set the capacity for a work center, navigate to :menuselection:`Manufacturing app -->
|
||||||
|
Configuration --> Work Centers`, and select a work center. On the :guilabel:`General Information`
|
||||||
|
tab, enter a numerical value in the :guilabel:`Capacity` field.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
A *drill station* work center has a capacity of one unit. An |MO| is confirmed for 10 units of a
|
||||||
|
*chair*, a product manufactured using the drill station.
|
||||||
|
|
||||||
|
Since there are ten times as many units to produce than the work center can handle at once, the
|
||||||
|
operation time is ten times the duration listed on the product's |BoM|.
|
||||||
|
|
||||||
|
|OEE| target
|
||||||
|
------------
|
||||||
|
|
||||||
|
The |OEE| target is the goal for how much of a work center's operating time should be fully
|
||||||
|
productive time. It is displayed as a percentage, and should only be set as high as `100%`.
|
||||||
|
|
||||||
|
To set the |OEE| target for a work center, navigate to :menuselection:`Manufacturing app -->
|
||||||
|
Configuration --> Settings --> Work Centers`, and select a work center. On the :guilabel:`General
|
||||||
|
Information` tab, enter a numerical value of `100.00` or less in the :guilabel:`OEE Target` field.
|
||||||
|
|
||||||
|
Calculating |OEE|
|
||||||
|
=================
|
||||||
|
|
||||||
|
|OEE| is represented as a percentage value between zero and 100. The value signifies the amount of
|
||||||
|
time that a work center was fully productive. The remainder signifies the amount of time that the
|
||||||
|
work center was operating at less than full efficiency. This can occur for a number of reasons,
|
||||||
|
including *reduced speed*, *material availability*, and *equipment failure*.
|
||||||
|
|
||||||
|
Fully productive time
|
||||||
|
---------------------
|
||||||
|
|
||||||
|
For a work center to be considered fully productive, it must be able to receive work orders, have
|
||||||
|
the components necessary to process work orders, and be operating within the expected duration of
|
||||||
|
the work order it is processing.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
An *assembly line* work center is not blocked, and receives a work order to assemble a *bicycle*.
|
||||||
|
The required components are available, so production begins as soon as they are picked and
|
||||||
|
delivered to the work center. The work order has an expected duration of 30 minutes, and is
|
||||||
|
completed in 27 minutes. All of this time is considered fully productive time.
|
||||||
|
|
||||||
|
Reduced speed
|
||||||
|
-------------
|
||||||
|
|
||||||
|
When a work center is operating at reduced speed, it means that it is processing a work order that
|
||||||
|
has exceeded its expected duration. While the work center may be operational, this is not considered
|
||||||
|
fully productive time.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
A *cutting station* work center receives a work order to cut boards for a *table*. The expected
|
||||||
|
duration of the work order is 15 minutes. The work order ends up taking 18 minutes to complete.
|
||||||
|
The work center is considered to have been operating at reduced speed during the three minutes
|
||||||
|
that exceeded the expected duration.
|
||||||
|
|
||||||
|
Material availability
|
||||||
|
---------------------
|
||||||
|
|
||||||
|
Material availability refers to situations where a work center is able to accept a work order, but
|
||||||
|
the required components are not available. This can occur because the components are not in stock,
|
||||||
|
or are reserved for a different order.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
Manufacturing of a *bench* requires 20 units of *wood*. A manufacturing order (MO) is confirmed
|
||||||
|
for 10 units of the bench, but there is not enough wood in stock to begin manufacturing. The time
|
||||||
|
it takes to acquire the wood is recorded as material availability downtime.
|
||||||
|
|
||||||
|
Equipment failure
|
||||||
|
-----------------
|
||||||
|
|
||||||
|
Equipment failure signifies any period of time when a work center is unusable due to maintenance
|
||||||
|
issues with its equipment. This can be due to equipment breaking down, or when a work center is shut
|
||||||
|
down for scheduled maintenance. In these cases, a work center can be blocked using a
|
||||||
|
:doc:`maintenance request <../../maintenance/maintenance_requests>`.
|
||||||
|
|
||||||
|
.. example::
|
||||||
|
The drill at a *drill station* work center breaks down, causing the work center to be unusable. A
|
||||||
|
maintenance request is created to fix the drill, and the work center is blocked from receiving
|
||||||
|
work orders. It takes two hours to fix the drill, and make the work center available again. This
|
||||||
|
two-hour period is recorded as equipment failure downtime.
|
||||||
|
|
||||||
|
|OEE| reporting
|
||||||
|
===============
|
||||||
|
|
||||||
|
To view |OEE| reporting metrics for every work center, navigate to :menuselection:`Manufacturing app
|
||||||
|
--> Reporting --> Overall Equipment Effectiveness`. This page shows the metrics for each work center
|
||||||
|
with |OEE| data.
|
||||||
|
|
||||||
|
Alternatively, to see |OEE| reporting metrics for a single work center, navigate to
|
||||||
|
:menuselection:`Manufacturing app --> Configuration --> Work Centers`, and select a work center. At
|
||||||
|
the top of the work center's form, click the :icon:`fa-pie-chart` :guilabel:`OEE` smart button.
|
||||||
|
|
||||||
|
By default, the main |OEE| reporting page shows data in a bar chart, while the page for a specific
|
||||||
|
work center shows it in a pie chart. To select a different chart type on either page, click the
|
||||||
|
:icon:`fa-bar-chart` :guilabel:`(bar chart)`, :icon:`fa-line-chart` :guilabel:`(line chart)`, or
|
||||||
|
:icon:`fa-pie-chart` :guilabel:`(pie chart)` button above the displayed chart.
|
||||||
|
|
||||||
|
It is also possible to see |OEE| data in a pivot view, or a list displaying each time entry, by
|
||||||
|
clicking the :icon:`oi-view-pivot` :guilabel:`(pivot view)` or :icon:`oi-view-list` :guilabel:`(list
|
||||||
|
view)` buttons at the top-right corner of the page.
|
||||||
|
|
||||||
|
.. image:: oee/oee-report.png
|
||||||
|
:align: center
|
||||||
|
:alt: The dashboard of the OEE report.
|
Binary file not shown.
After Width: | Height: | Size: 11 KiB |
Loading…
Reference in New Issue
Block a user