Planning
|
||||
========
|
||||
|
||||
.. toctree::
|
||||
:titlesonly:
|
||||
:glob:
|
||||
|
||||
planning/scheduled_date
|
BIN
inventory/management/planning/media/scheduled_date_01.png
Normal file
After Width: | Height: | Size: 20 KiB |
BIN
inventory/management/planning/media/scheduled_date_02.png
Normal file
After Width: | Height: | Size: 11 KiB |
BIN
inventory/management/planning/media/scheduled_date_03.png
Normal file
After Width: | Height: | Size: 21 KiB |
BIN
inventory/management/planning/media/scheduled_date_04.png
Normal file
After Width: | Height: | Size: 7.0 KiB |
BIN
inventory/management/planning/media/scheduled_date_05.png
Normal file
After Width: | Height: | Size: 7.0 KiB |
BIN
inventory/management/planning/media/scheduled_date_06.png
Normal file
After Width: | Height: | Size: 9.1 KiB |
BIN
inventory/management/planning/media/scheduled_date_07.png
Normal file
After Width: | Height: | Size: 19 KiB |
BIN
inventory/management/planning/media/scheduled_date_08.png
Normal file
After Width: | Height: | Size: 20 KiB |
BIN
inventory/management/planning/media/scheduled_date_09.png
Normal file
After Width: | Height: | Size: 31 KiB |
187
inventory/management/planning/scheduled_date.rst
Normal file
@ -0,0 +1,187 @@
|
||||
============================================
|
||||
How is the Scheduled Delivery Date Computed?
|
||||
============================================
|
||||
|
||||
In most cases, scheduled dates are computed to be able to plan
|
||||
deliveries, receptions, and so on. Depending on your company’s habits,
|
||||
Odoo generates scheduled dates via the scheduler.
|
||||
|
||||
To make your life easier, the Odoo scheduler computes everything per
|
||||
line, whether it’s a manufacturing order, a delivery order, a sale
|
||||
order, etc.
|
||||
|
||||
.. note::
|
||||
The computed dates are dependent on the different lead times configured
|
||||
in Odoo.
|
||||
|
||||
Configuring lead times
|
||||
======================
|
||||
|
||||
Configuring lead times is the first move if you want to compute
|
||||
scheduled dates. Those are the delays promised (in terms of delivery,
|
||||
manufacturing, etc.) to your partners and/or clients.
|
||||
|
||||
.. note::
|
||||
In Odoo, you can configure different lead times.
|
||||
|
||||
At a product level
|
||||
------------------
|
||||
|
||||
When configuring lead times at the product level, you have three
|
||||
different types to take into account: supplier lead time, customer lead
|
||||
time, and manufacturing lead time.
|
||||
|
||||
Supplier lead time
|
||||
~~~~~~~~~~~~~~~~~~
|
||||
|
||||
The supplier lead time is the time needed for the supplier to deliver
|
||||
your purchased products. To configure it, select a product and click on
|
||||
the inventory tab. There, you will have to add a vendor to your product.
|
||||
|
||||
.. image:: media/scheduled_date_01.png
|
||||
:align: center
|
||||
|
||||
Now, just open the vendor form and fill its *Delivery lead time*. In
|
||||
this case, the delivery day will be equal to *Date of the Purchase
|
||||
Order + Delivery Lead Time*.
|
||||
|
||||
.. image:: media/scheduled_date_02.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
Do not forget that it is possible to add different vendor pricelists
|
||||
and, thus, different delivery lead times, depending on the vendor.
|
||||
|
||||
Customer Lead Time
|
||||
~~~~~~~~~~~~~~~~~~
|
||||
|
||||
It is the time needed to get your product from your store/warehouse to
|
||||
your customer. It can be configured for any product. To add it, select a
|
||||
product and go to the inventory tab. There, simply indicate your
|
||||
*customer lead time*.
|
||||
|
||||
.. image:: media/scheduled_date_03.png
|
||||
:align: center
|
||||
|
||||
Manufacturing lead time
|
||||
~~~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
On the same page, it is possible to configure what’s called the
|
||||
*Manufacturing Lead Time*. It is the time needed to manufacture the
|
||||
product.
|
||||
|
||||
At the company level
|
||||
--------------------
|
||||
|
||||
At the company level, you can configure security days. Those are useful
|
||||
to cope with eventual dalys and to be sure to meet your engagements. The
|
||||
idea is to subtract backup days from the computed scheduled date in case
|
||||
of delays.
|
||||
|
||||
Once again, there are three different types of security lead times: for
|
||||
sales, for purchases, and for manufacturing.
|
||||
|
||||
Security lead time for sales
|
||||
~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
In sales, security lead time corresponds to backup days to ensure you
|
||||
will be able to deliver your clients in times. They are margins of
|
||||
errors for delivery lead times. Security days are the same logic as the
|
||||
early wristwatch, in order to arrive on time.
|
||||
|
||||
The idea is to subtract the numbers of security days from the
|
||||
calculation and, thus, to compute a scheduled date earlier than the one
|
||||
you promised to your client. In that way, you are sure to be able to
|
||||
keep your commitment.
|
||||
|
||||
To set up your security dates, go to *Inventory > Configuration >
|
||||
Settings* and enable the feature.
|
||||
|
||||
.. image:: media/scheduled_date_04.png
|
||||
:align: center
|
||||
|
||||
Security lead time for purchase
|
||||
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
It follows the same logic as security lead time for sales except that
|
||||
security lead time for purchase is the margin of error for vendor lead
|
||||
times, not for sales.
|
||||
|
||||
When the system generates purchase orders for procuring products, they
|
||||
will be scheduled that many days earlier to cope with unexpected vendor
|
||||
delays.
|
||||
|
||||
To find purchase lead time, go to *Inventory > Configuration >
|
||||
Settings* and enable the feature.
|
||||
|
||||
.. image:: media/scheduled_date_05.png
|
||||
:align: center
|
||||
|
||||
Security lead time for manufacturing
|
||||
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
The security lead time for manufacturing allows generating manufacturing
|
||||
orders which are scheduled that many days earlier to cope with
|
||||
unexpected manufacturing days.
|
||||
|
||||
To configure it, go to *Manufacturing > Configuration > Settings* and
|
||||
enable the *Security Lead Time* option. Then, hit save.
|
||||
|
||||
.. image:: media/scheduled_date_06.png
|
||||
:align: center
|
||||
|
||||
At route level
|
||||
--------------
|
||||
|
||||
Sometimes, the internal transfers that a product might do may also
|
||||
influence the computed date. The delays due to internal transfers can be
|
||||
specified in the *Inventory* app when you create a new rule in a
|
||||
route.
|
||||
|
||||
To specify them, go to *Inventory > Configuration > Routes* and add a
|
||||
push rule to set a delay. Of course, you need to activate *Multi-step
|
||||
Routes* to use this feature.
|
||||
|
||||
.. image:: media/scheduled_date_07.png
|
||||
:align: center
|
||||
|
||||
At the sale order level
|
||||
-----------------------
|
||||
|
||||
Expected date
|
||||
~~~~~~~~~~~~~
|
||||
|
||||
In the *Sales* application, you have the possibility to activate the
|
||||
option *Delivery Date*. It will allow you to see additional fields on
|
||||
the sale order.
|
||||
|
||||
By enabling this option, Odoo will indicate the *Expected Date* in the
|
||||
*Other Info* tab of the sales order. This one is automatically
|
||||
computed based on the different lead times.
|
||||
|
||||
.. image:: media/scheduled_date_08.png
|
||||
:align: center
|
||||
|
||||
If you set a *Commitment Date* to deliver your customer that is
|
||||
earlier than the *Expected Date*, a warning message will appear on the
|
||||
screen.
|
||||
|
||||
.. image:: media/scheduled_date_09.png
|
||||
:align: center
|
||||
|
||||
Example
|
||||
~~~~~~~
|
||||
|
||||
To better understand all the above info, here is an example. You may
|
||||
sell a car today (January 1st), that is purchased on order, and you
|
||||
promise to deliver your customer within 20 days (January 20th). In such
|
||||
a scenario, the scheduler will trigger the following events, based on
|
||||
your configuration:
|
||||
|
||||
- January 19: this is the actual scheduled delivery (1 day of Sales Safety Days);
|
||||
|
||||
- January 18: you receive the product from your supplier (1 day of Purchase days);
|
||||
|
||||
- January 10: this is the deadline to order at your supplier (9 days of Supplier Delivery Lead Time);
|
||||
|
||||
- January 8: trigger a purchase request to your purchase team, since they need, on average, 2 days to find the right supplier and order.
|