Planning
|
||||||
|
========
|
||||||
|
|
||||||
|
.. toctree::
|
||||||
|
:titlesonly:
|
||||||
|
:glob:
|
||||||
|
|
||||||
|
planning/scheduled_date
|
BIN
inventory/management/planning/media/scheduled_date_01.png
Normal file
After Width: | Height: | Size: 20 KiB |
BIN
inventory/management/planning/media/scheduled_date_02.png
Normal file
After Width: | Height: | Size: 11 KiB |
BIN
inventory/management/planning/media/scheduled_date_03.png
Normal file
After Width: | Height: | Size: 21 KiB |
BIN
inventory/management/planning/media/scheduled_date_04.png
Normal file
After Width: | Height: | Size: 7.0 KiB |
BIN
inventory/management/planning/media/scheduled_date_05.png
Normal file
After Width: | Height: | Size: 7.0 KiB |
BIN
inventory/management/planning/media/scheduled_date_06.png
Normal file
After Width: | Height: | Size: 9.1 KiB |
BIN
inventory/management/planning/media/scheduled_date_07.png
Normal file
After Width: | Height: | Size: 19 KiB |
BIN
inventory/management/planning/media/scheduled_date_08.png
Normal file
After Width: | Height: | Size: 20 KiB |
BIN
inventory/management/planning/media/scheduled_date_09.png
Normal file
After Width: | Height: | Size: 31 KiB |
187
inventory/management/planning/scheduled_date.rst
Normal file
@ -0,0 +1,187 @@
|
|||||||
|
============================================
|
||||||
|
How is the Scheduled Delivery Date Computed?
|
||||||
|
============================================
|
||||||
|
|
||||||
|
In most cases, scheduled dates are computed to be able to plan
|
||||||
|
deliveries, receptions, and so on. Depending on your company’s habits,
|
||||||
|
Odoo generates scheduled dates via the scheduler.
|
||||||
|
|
||||||
|
To make your life easier, the Odoo scheduler computes everything per
|
||||||
|
line, whether it’s a manufacturing order, a delivery order, a sale
|
||||||
|
order, etc.
|
||||||
|
|
||||||
|
.. note::
|
||||||
|
The computed dates are dependent on the different lead times configured
|
||||||
|
in Odoo.
|
||||||
|
|
||||||
|
Configuring lead times
|
||||||
|
======================
|
||||||
|
|
||||||
|
Configuring lead times is the first move if you want to compute
|
||||||
|
scheduled dates. Those are the delays promised (in terms of delivery,
|
||||||
|
manufacturing, etc.) to your partners and/or clients.
|
||||||
|
|
||||||
|
.. note::
|
||||||
|
In Odoo, you can configure different lead times.
|
||||||
|
|
||||||
|
At a product level
|
||||||
|
------------------
|
||||||
|
|
||||||
|
When configuring lead times at the product level, you have three
|
||||||
|
different types to take into account: supplier lead time, customer lead
|
||||||
|
time, and manufacturing lead time.
|
||||||
|
|
||||||
|
Supplier lead time
|
||||||
|
~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
The supplier lead time is the time needed for the supplier to deliver
|
||||||
|
your purchased products. To configure it, select a product and click on
|
||||||
|
the inventory tab. There, you will have to add a vendor to your product.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_01.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
Now, just open the vendor form and fill its *Delivery lead time*. In
|
||||||
|
this case, the delivery day will be equal to *Date of the Purchase
|
||||||
|
Order + Delivery Lead Time*.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_02.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
.. tip::
|
||||||
|
Do not forget that it is possible to add different vendor pricelists
|
||||||
|
and, thus, different delivery lead times, depending on the vendor.
|
||||||
|
|
||||||
|
Customer Lead Time
|
||||||
|
~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
It is the time needed to get your product from your store/warehouse to
|
||||||
|
your customer. It can be configured for any product. To add it, select a
|
||||||
|
product and go to the inventory tab. There, simply indicate your
|
||||||
|
*customer lead time*.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_03.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
Manufacturing lead time
|
||||||
|
~~~~~~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
On the same page, it is possible to configure what’s called the
|
||||||
|
*Manufacturing Lead Time*. It is the time needed to manufacture the
|
||||||
|
product.
|
||||||
|
|
||||||
|
At the company level
|
||||||
|
--------------------
|
||||||
|
|
||||||
|
At the company level, you can configure security days. Those are useful
|
||||||
|
to cope with eventual dalys and to be sure to meet your engagements. The
|
||||||
|
idea is to subtract backup days from the computed scheduled date in case
|
||||||
|
of delays.
|
||||||
|
|
||||||
|
Once again, there are three different types of security lead times: for
|
||||||
|
sales, for purchases, and for manufacturing.
|
||||||
|
|
||||||
|
Security lead time for sales
|
||||||
|
~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
In sales, security lead time corresponds to backup days to ensure you
|
||||||
|
will be able to deliver your clients in times. They are margins of
|
||||||
|
errors for delivery lead times. Security days are the same logic as the
|
||||||
|
early wristwatch, in order to arrive on time.
|
||||||
|
|
||||||
|
The idea is to subtract the numbers of security days from the
|
||||||
|
calculation and, thus, to compute a scheduled date earlier than the one
|
||||||
|
you promised to your client. In that way, you are sure to be able to
|
||||||
|
keep your commitment.
|
||||||
|
|
||||||
|
To set up your security dates, go to *Inventory > Configuration >
|
||||||
|
Settings* and enable the feature.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_04.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
Security lead time for purchase
|
||||||
|
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
It follows the same logic as security lead time for sales except that
|
||||||
|
security lead time for purchase is the margin of error for vendor lead
|
||||||
|
times, not for sales.
|
||||||
|
|
||||||
|
When the system generates purchase orders for procuring products, they
|
||||||
|
will be scheduled that many days earlier to cope with unexpected vendor
|
||||||
|
delays.
|
||||||
|
|
||||||
|
To find purchase lead time, go to *Inventory > Configuration >
|
||||||
|
Settings* and enable the feature.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_05.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
Security lead time for manufacturing
|
||||||
|
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
The security lead time for manufacturing allows generating manufacturing
|
||||||
|
orders which are scheduled that many days earlier to cope with
|
||||||
|
unexpected manufacturing days.
|
||||||
|
|
||||||
|
To configure it, go to *Manufacturing > Configuration > Settings* and
|
||||||
|
enable the *Security Lead Time* option. Then, hit save.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_06.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
At route level
|
||||||
|
--------------
|
||||||
|
|
||||||
|
Sometimes, the internal transfers that a product might do may also
|
||||||
|
influence the computed date. The delays due to internal transfers can be
|
||||||
|
specified in the *Inventory* app when you create a new rule in a
|
||||||
|
route.
|
||||||
|
|
||||||
|
To specify them, go to *Inventory > Configuration > Routes* and add a
|
||||||
|
push rule to set a delay. Of course, you need to activate *Multi-step
|
||||||
|
Routes* to use this feature.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_07.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
At the sale order level
|
||||||
|
-----------------------
|
||||||
|
|
||||||
|
Expected date
|
||||||
|
~~~~~~~~~~~~~
|
||||||
|
|
||||||
|
In the *Sales* application, you have the possibility to activate the
|
||||||
|
option *Delivery Date*. It will allow you to see additional fields on
|
||||||
|
the sale order.
|
||||||
|
|
||||||
|
By enabling this option, Odoo will indicate the *Expected Date* in the
|
||||||
|
*Other Info* tab of the sales order. This one is automatically
|
||||||
|
computed based on the different lead times.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_08.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
If you set a *Commitment Date* to deliver your customer that is
|
||||||
|
earlier than the *Expected Date*, a warning message will appear on the
|
||||||
|
screen.
|
||||||
|
|
||||||
|
.. image:: media/scheduled_date_09.png
|
||||||
|
:align: center
|
||||||
|
|
||||||
|
Example
|
||||||
|
~~~~~~~
|
||||||
|
|
||||||
|
To better understand all the above info, here is an example. You may
|
||||||
|
sell a car today (January 1st), that is purchased on order, and you
|
||||||
|
promise to deliver your customer within 20 days (January 20th). In such
|
||||||
|
a scenario, the scheduler will trigger the following events, based on
|
||||||
|
your configuration:
|
||||||
|
|
||||||
|
- January 19: this is the actual scheduled delivery (1 day of Sales Safety Days);
|
||||||
|
|
||||||
|
- January 18: you receive the product from your supplier (1 day of Purchase days);
|
||||||
|
|
||||||
|
- January 10: this is the deadline to order at your supplier (9 days of Supplier Delivery Lead Time);
|
||||||
|
|
||||||
|
- January 8: trigger a purchase request to your purchase team, since they need, on average, 2 days to find the right supplier and order.
|