Work order dependencies
|
||||
=======================
|
||||
|
||||
.. |BOM| replace:: :abbr:`BoM (Bill of Materials)`
|
||||
|
||||
When manufacturing certain products, specific operations may need to be completed before others can
|
||||
begin. In order to ensure operations are carried out in the correct order, Odoo *Manufacturing*
|
||||
features a *work order dependencies* setting. Enabling this setting allows for operations on a Bill
|
||||
of Materials (BoM) to be *blocked* by other operations that should occur first.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
The *work order dependencies* setting is not enabled by default. To enable it, begin by navigating
|
||||
to :menuselection:`Manufacturing --> Configuration --> Settings`. Then, enable the :guilabel:`Work
|
||||
Orders` setting, if it is not already active.
|
||||
|
||||
After enabling the :guilabel:`Work Orders` setting, the :guilabel:`Work Order Dependencies` setting
|
||||
appears below it. Enable :guilabel:`Work Order Dependencies`, then click :guilabel:`Save` to confirm
|
||||
the changes.
|
||||
|
||||
Add dependencies to BoM
|
||||
=======================
|
||||
|
||||
Work order dependencies are configured on a product's |BOM|. To do so, navigate to
|
||||
:menuselection:`Manufacturing --> Products --> Bills of Materials`, then select a |BOM|, or create a
|
||||
new one by clicking :guilabel:`New`.
|
||||
|
||||
.. admonition:: Learn more
|
||||
|
||||
For a complete guide on how to properly configure a new |BOM|, see the documentation on
|
||||
:ref:`creating a bill of materials <manufacturing/management/bill-configuration>`.
|
||||
|
||||
On the |BOM|, click on the :guilabel:`Miscellaneous` tab, then enable the :guilabel:`Operation
|
||||
Dependencies` checkbox. This makes a new :guilabel:`Blocked By` option available in the settings of
|
||||
the :guilabel:`Operations` tab.
|
||||
|
||||
.. image:: work_order_dependencies/operation-dependencies.png
|
||||
:align: center
|
||||
:alt: The Operation Dependencies checkbox on the Miscellaneous tab of a BoM.
|
||||
|
||||
Next, click on the :guilabel:`Operations` tab. On the top-right of the tab, click on the tab's
|
||||
:guilabel:`settings` button, then enable the :guilabel:`Blocked By` checkbox. This makes a
|
||||
:guilabel:`Blocked By` field appear for each operation on the :guilabel:`Operations` tab.
|
||||
|
||||
.. image:: work_order_dependencies/operations-settings.png
|
||||
:align: center
|
||||
:alt: The settings for the Operations tab on a BoM.
|
||||
|
||||
In the line of the operation that should be blocked by another operation, click the
|
||||
:guilabel:`Blocked By` field, and an :guilabel:`Open: Operations` pop-up window appears. In the
|
||||
:guilabel:`Blocked By` drop-down field on the pop-up window, select the blocking operation that must
|
||||
be completed *before* the operation that is blocked.
|
||||
|
||||
.. image:: work_order_dependencies/blocked-by.png
|
||||
:align: center
|
||||
:alt: The Blocked By drop-down field for an operation on a BoM.
|
||||
|
||||
Finally, save the |BOM| by clicking :guilabel:`Save`.
|
||||
|
||||
Plan work orders using dependencies
|
||||
===================================
|
||||
|
||||
Once work order dependencies have been configured on a |BOM|, Odoo *Manufacturing* is able to plan
|
||||
when work orders are scheduled, based on their dependencies. To plan the work orders for a
|
||||
manufacturing order, begin by navigating to :menuselection:`Manufacturing --> Operations -->
|
||||
Manufacturing Orders`.
|
||||
|
||||
Next, select a manufacturing order for a product with work order dependencies set on its |BOM|, or
|
||||
create a new manufacturing order by clicking :guilabel:`New`. If a new manufacturing order is
|
||||
created, select a |BOM| configured with work order dependencies from the :guilabel:`Bill of
|
||||
Material` drop-down field, then click :guilabel:`Confirm`.
|
||||
|
||||
After confirming the manufacturing order, select the :guilabel:`Work Orders` tab to view the work
|
||||
orders required to complete it. Any work orders that are *not* blocked by a different work order
|
||||
display a `Ready` tag in the :guilabel:`Status` section.
|
||||
|
||||
Work orders that are blocked by one or more work orders display a `Waiting for another WO` tag
|
||||
instead. Once the blocking work order(s) are completed, the tag updates to `Ready`.
|
||||
|
||||
.. image:: work_order_dependencies/work-order-status.png
|
||||
:align: center
|
||||
:alt: The status tags for work orders on a manufacturing order.
|
||||
|
||||
To schedule the manufacturing order's work orders, click the :guilabel:`Plan` button at the top of
|
||||
the page. After doing so, the :guilabel:`Scheduled Start Date` field for each work order on the
|
||||
:guilabel:`Work Orders` tab auto-fills with the scheduled start date and time. A blocked work order
|
||||
is scheduled at the end of the time period specified in the :guilabel:`Expected Duration` field of
|
||||
the work order that precedes it.
|
||||
|
||||
.. image:: work_order_dependencies/scheduled-start-date.png
|
||||
:align: center
|
||||
:alt: The Scheduled Start Date field for work orders on a manufacturing order.
|
||||
|
||||
.. example::
|
||||
A manufacturing order is created for Product A. The manufacturing order has two operations: Cut
|
||||
and Assemble. Each operation has an expected duration of 60 minutes, and the Assemble operation
|
||||
is blocked by the Cut operation.
|
||||
|
||||
The :guilabel:`Plan` button for the manufacturing order is clicked at 1:30 pm, and the Cut
|
||||
operation is scheduled to begin immediately. Since the Cut operation has an expected duration of
|
||||
60 minutes, the Assemble operation is scheduled to begin at 2:30 pm.
|
||||
|
||||
Planning by workcenter
|
||||
----------------------
|
||||
|
||||
To see a visual representation of how work orders are planned, navigate to the :guilabel:`Work
|
||||
Orders Planning` page by going to :menuselection:`Manufacturing --> Planning --> Planning by
|
||||
Workcenter`. This page shows a timeline of all the work orders scheduled for each operation.
|
||||
|
||||
If one work order is blocked by the completion of another, the work order that is blocked is shown
|
||||
as scheduled to start after the work order blocking it. In addition, an arrow connects the two work
|
||||
orders, leading from the blocking operation to the blocked operation.
|
||||
|
||||
.. image:: work_order_dependencies/planning-arrow.png
|
||||
:align: center
|
||||
:alt: The arrow connecting a blocked work order to the work order blocking it.
|
Binary file not shown.
After Width: | Height: | Size: 14 KiB |
Binary file not shown.
After Width: | Height: | Size: 14 KiB |
Binary file not shown.
After Width: | Height: | Size: 3.6 KiB |
Binary file not shown.
After Width: | Height: | Size: 1.2 KiB |
Binary file not shown.
After Width: | Height: | Size: 20 KiB |
Binary file not shown.
After Width: | Height: | Size: 9.5 KiB |
Loading…
Reference in New Issue
Block a user