[FIX] MRP: Update using work centers for 15.0

closes odoo/documentation#3776

Signed-off-by: Zachary Straub (zst) <zst@odoo.com>
This commit is contained in:
John Holton (hojo) 2023-03-08 19:59:37 +00:00 committed by Zachary Straub (ZST)
parent 5a66befeed
commit 8606c2185f
7 changed files with 17 additions and 16 deletions

View File

@ -2,25 +2,26 @@
Manage work orders using work centers Manage work orders using work centers
===================================== =====================================
Odoo Manufacturing allows for work orders to be carried out at specific work centers. When a Odoo *Manufacturing* allows for work orders to be carried out at specific work centers. When a
manufacturing order is created for a product, any work orders listed in the :guilabel:`Operations` manufacturing order is created for a product, any work orders listed in the :guilabel:`Operations`
tab of the product bill of materials (BoM) will be automatically created as well and assigned to the tab of the product *Bill of Materials* (*BoM*) will be automatically created as well and assigned to
specified work center. Work orders can be managed in the :guilabel:`Manufacturing` module by the specified work center. Work orders can be managed in the :menuselection:`Manufacturing` module
selecting :menuselection:`Operations --> Work Orders`. by selecting :menuselection:`Operations --> Work Orders`.
In order to use work centers, the :guilabel:`Work Orders` feature must first be enabled. To do so, In order to use work centers, the :guilabel:`Work Orders` feature must first be enabled. To do so,
go to the :guilabel:`Manufacturing` module, select :menuselection:`Configuration --> Settings`, and go to the :menuselection:`Manufacturing` module, select :menuselection:`Configuration --> Settings`,
activate the checkbox next to :guilabel:`Work Orders`. Work centers can then be created and managed and activate the checkbox next to :guilabel:`Work Orders`. Work centers can then be created and
by selecting :menuselection:`Configuration --> Work Centers`. managed by selecting :menuselection:`Configuration --> Work Centers`.
Create a work center Create a work center
==================== ====================
Within the :guilabel:`Manufacturing` module, select :menuselection:`Configuration --> Work Centers Within the :menuselection:`Manufacturing` module, select :menuselection:`Configuration --> Work
--> Create`. The work center form can then be filled out as follows: Centers --> Create`. The work center form can then be filled out as follows:
- :guilabel:`Work Center Name`: give the work center a concise name that describes the type of - :guilabel:`Work Center Name`: give the work center a concise name that describes the type of
operations it will be used for operations it will be used for
- :guilabel:`Tag`: assign the work center one or more user-created tags
- :guilabel:`Alternative Workcenters`: specify an alternative work center for operations to be - :guilabel:`Alternative Workcenters`: specify an alternative work center for operations to be
carried out at if the main work center is not available carried out at if the main work center is not available
- :guilabel:`Code`: assign the work center a reference code - :guilabel:`Code`: assign the work center a reference code
@ -43,8 +44,8 @@ assigned to a work center:
- :guilabel:`Capacity`: the number of operations that can be performed at the work center - :guilabel:`Capacity`: the number of operations that can be performed at the work center
simultaneously simultaneously
- :guilabel:`OEE Target`: the target for efficiency at the work center - :guilabel:`OEE Target`: the target for efficiency at the work center
- :guilabel:`Time before prod.`: setup time required before work can commence - :guilabel:`Setup Time`: time required to set up the work center before work can commence
- :guilabel:`Time after prod.`: breakdown or cleanup time required after work is finished - :guilabel:`Cleanup Time`: time required to clean the work center after work is finished
- :guilabel:`Cost per hour`: the cost of operating the work center for one hour - :guilabel:`Cost per hour`: the cost of operating the work center for one hour
- :guilabel:`Analytic Account`: the account where the cost of the work center should be recorded - :guilabel:`Analytic Account`: the account where the cost of the work center should be recorded
@ -120,9 +121,9 @@ automatically changed to the alternative work center.
Monitor work center performance Monitor work center performance
=============================== ===============================
Performance for an individual work center can be viewed by selecting Performance for an individual work center can be viewed by selecting :menuselection:`Configuration
:menuselection:`Configuration --> Work Centers`, and clicking on a work center. A variety of metrics --> Work Centers`, and clicking on a work center. A variety of metrics showing work center
showing work center performance can be viewed at the top right of the form: performance can be viewed at the top right of the form:
- :guilabel:`OEE`: overall effective efficiency, the percentage of time that the work center has - :guilabel:`OEE`: overall effective efficiency, the percentage of time that the work center has
been fully productive been fully productive

Binary file not shown.

Before

Width:  |  Height:  |  Size: 23 KiB

After

Width:  |  Height:  |  Size: 23 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 22 KiB

After

Width:  |  Height:  |  Size: 22 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 11 KiB

After

Width:  |  Height:  |  Size: 13 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 9.7 KiB

After

Width:  |  Height:  |  Size: 12 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 11 KiB

After

Width:  |  Height:  |  Size: 14 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 8.9 KiB

After

Width:  |  Height:  |  Size: 8.9 KiB