[FIX] MRP: Update using work centers for 15.0

closes odoo/documentation#3776

Signed-off-by: Zachary Straub (zst) <zst@odoo.com>
This commit is contained in:
John Holton (hojo) 2023-03-08 19:59:37 +00:00 committed by Zachary Straub (ZST)
parent 5a66befeed
commit 8606c2185f
7 changed files with 17 additions and 16 deletions

View File

@ -2,25 +2,26 @@
Manage work orders using work centers
=====================================
Odoo Manufacturing allows for work orders to be carried out at specific work centers. When a
Odoo *Manufacturing* allows for work orders to be carried out at specific work centers. When a
manufacturing order is created for a product, any work orders listed in the :guilabel:`Operations`
tab of the product bill of materials (BoM) will be automatically created as well and assigned to the
specified work center. Work orders can be managed in the :guilabel:`Manufacturing` module by
selecting :menuselection:`Operations --> Work Orders`.
tab of the product *Bill of Materials* (*BoM*) will be automatically created as well and assigned to
the specified work center. Work orders can be managed in the :menuselection:`Manufacturing` module
by selecting :menuselection:`Operations --> Work Orders`.
In order to use work centers, the :guilabel:`Work Orders` feature must first be enabled. To do so,
go to the :guilabel:`Manufacturing` module, select :menuselection:`Configuration --> Settings`, and
activate the checkbox next to :guilabel:`Work Orders`. Work centers can then be created and managed
by selecting :menuselection:`Configuration --> Work Centers`.
go to the :menuselection:`Manufacturing` module, select :menuselection:`Configuration --> Settings`,
and activate the checkbox next to :guilabel:`Work Orders`. Work centers can then be created and
managed by selecting :menuselection:`Configuration --> Work Centers`.
Create a work center
====================
Within the :guilabel:`Manufacturing` module, select :menuselection:`Configuration --> Work Centers
--> Create`. The work center form can then be filled out as follows:
Within the :menuselection:`Manufacturing` module, select :menuselection:`Configuration --> Work
Centers --> Create`. The work center form can then be filled out as follows:
- :guilabel:`Work Center Name`: give the work center a concise name that describes the type of
operations it will be used for
- :guilabel:`Tag`: assign the work center one or more user-created tags
- :guilabel:`Alternative Workcenters`: specify an alternative work center for operations to be
carried out at if the main work center is not available
- :guilabel:`Code`: assign the work center a reference code
@ -43,8 +44,8 @@ assigned to a work center:
- :guilabel:`Capacity`: the number of operations that can be performed at the work center
simultaneously
- :guilabel:`OEE Target`: the target for efficiency at the work center
- :guilabel:`Time before prod.`: setup time required before work can commence
- :guilabel:`Time after prod.`: breakdown or cleanup time required after work is finished
- :guilabel:`Setup Time`: time required to set up the work center before work can commence
- :guilabel:`Cleanup Time`: time required to clean the work center after work is finished
- :guilabel:`Cost per hour`: the cost of operating the work center for one hour
- :guilabel:`Analytic Account`: the account where the cost of the work center should be recorded
@ -72,8 +73,8 @@ to a work center. The following information will be displayed for each piece of
:alt: The equipment tab of the work center form.
.. note::
:guilabel:`MTBF`, :guilabel:`MTTR`, and :guilabel:`Est. Next Failure` are all calculated
automatically based on past failure data, if any exists.
:guilabel:`MTBF`, :guilabel:`MTTR`, and :guilabel:`Est. Next Failure` are all calculated
automatically based on past failure data, if any exists.
Integrate IoT devices
---------------------
@ -120,9 +121,9 @@ automatically changed to the alternative work center.
Monitor work center performance
===============================
Performance for an individual work center can be viewed by selecting
:menuselection:`Configuration --> Work Centers`, and clicking on a work center. A variety of metrics
showing work center performance can be viewed at the top right of the form:
Performance for an individual work center can be viewed by selecting :menuselection:`Configuration
--> Work Centers`, and clicking on a work center. A variety of metrics showing work center
performance can be viewed at the top right of the form:
- :guilabel:`OEE`: overall effective efficiency, the percentage of time that the work center has
been fully productive

Binary file not shown.

Before

Width:  |  Height:  |  Size: 23 KiB

After

Width:  |  Height:  |  Size: 23 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 22 KiB

After

Width:  |  Height:  |  Size: 22 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 11 KiB

After

Width:  |  Height:  |  Size: 13 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 9.7 KiB

After

Width:  |  Height:  |  Size: 12 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 11 KiB

After

Width:  |  Height:  |  Size: 14 KiB

Binary file not shown.

Before

Width:  |  Height:  |  Size: 8.9 KiB

After

Width:  |  Height:  |  Size: 8.9 KiB