[ADD] project: How to plan and track employees' assignments?
https://docs.google.com/document/d/1tCBF6GE1nNo_0SMN-dvG9s27eto3kUU6y8Lx5dyv_ok/edit?usp=sharing
@ -1,3 +1,138 @@
|
||||
=============================================
|
||||
How to plan and track employees' assignments?
|
||||
=============================================
|
||||
=============================================
|
||||
|
||||
Following and planning your employees' assignments can be a heavy
|
||||
challenge especially when you manage several people. Luckily, using Odoo
|
||||
Project, you can handle it in only a couple of clicks.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
The only necessary configuration is to install the **Project Management**
|
||||
module. To do so, go in the application module, search for project and
|
||||
install the application.
|
||||
|
||||
.. image:: media/assignments01.png
|
||||
:align: center
|
||||
|
||||
If you wish to manage time estimation, you will need to enable
|
||||
timesheets on tasks. From the **Project** application, go to
|
||||
:menuselection:`Configuration --> Settings` in the dropdown menu.
|
||||
Then, under **Time Work Estimation**, select the **manage time
|
||||
estimation on tasks** option. Do not forget to apply your changes.
|
||||
|
||||
.. image:: media/assignments02.png
|
||||
:align: center
|
||||
|
||||
This feature will create a progress bar in the form view of your tasks.
|
||||
Every time your salesperson will add working time in his timesheet, the
|
||||
bar will be updated accordingly, based on the initially planned hours.
|
||||
|
||||
.. image:: media/assignments03.png
|
||||
:align: center
|
||||
|
||||
Manage tasks with views
|
||||
=======================
|
||||
|
||||
You can have an overview of your different task thanks to the multiple
|
||||
views available with Odoo. Three main views will help you to plan and
|
||||
follow up on your employees' tasks: the kanban view, the list view
|
||||
(using timesheets) and the calendar view.
|
||||
|
||||
Create and edit tasks in order to fill up your pipeline. Don't forget to
|
||||
fill in a responsible person and an estimated time if you have one.
|
||||
|
||||
Get an overview of activities with the kanban view
|
||||
--------------------------------------------------
|
||||
|
||||
The Kanban view is a post-it like view, divided in different stages. It
|
||||
enables you to have a clear view on the stages your tasks are in and the
|
||||
ones having the higher priorities.
|
||||
|
||||
The Kanban view is the default view when accessing a project, but if you
|
||||
are on another view, you can go back to it any time by clicking the
|
||||
kanban view logo in the upper right corner
|
||||
|
||||
.. image:: media/assignments04.png
|
||||
:align: center
|
||||
|
||||
Add/rearrange stages
|
||||
~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
You can easily personalize your project to suit your business needs by
|
||||
creating new columns. From the Kanban view of your project, you can add
|
||||
stages by clicking on **Add new column** (see image below). If you
|
||||
want to rearrange the order of your stages, you can easily do so by
|
||||
dragging and dropping the column you want to move to the desired
|
||||
location. You can also fold or unfold your stages by using the **setting**
|
||||
icon on your desired stage.
|
||||
|
||||
.. image:: media/assignments06.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
Create one column per stage in your working process. For example,
|
||||
in a development project, stages might be: Specifications,
|
||||
Development, Test, Done.
|
||||
|
||||
Sort tasks by priority
|
||||
~~~~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
On each one of your columns, you have the ability to sort your tasks by
|
||||
priority. Tasks with a higher priority will automatically be moved to
|
||||
the top of the column. From the Kanban view, click on the star in the
|
||||
bottom left of a task to tag it as **high priority**. For the tasks that
|
||||
are not tagged, Odoo will automatically classify them according to their
|
||||
deadlines.
|
||||
|
||||
Note that dates that passed their deadlines will appear in red( in the
|
||||
list view too) so you can easily follow up the progression of different
|
||||
tasks.
|
||||
|
||||
.. image:: media/assignments07.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
Don't forget you can filter your tasks with the filter menu.
|
||||
|
||||
Track the progress of each task with the list view
|
||||
--------------------------------------------------
|
||||
|
||||
If you enabled the **Manage Time Estimation on Tasks**, your employees
|
||||
will be able to log their activities on tasks under the **Timesheets**
|
||||
sub-menu along with their duration. The **Working Time Progress** bar will
|
||||
be updated each time the employee will add an activity.
|
||||
|
||||
.. image:: media/assignments08.png
|
||||
:align: center
|
||||
|
||||
As a manager, you can easily overview the time spent on tasks for all
|
||||
employees by using the list view. To do so, access the project of your
|
||||
choice and click on the List view icon (see below). The last column will
|
||||
show you the progression of each task.
|
||||
|
||||
.. image:: media/assignments09.png
|
||||
:align: center
|
||||
|
||||
Keep an eye on deadlines with the Calendar view
|
||||
-----------------------------------------------
|
||||
|
||||
If you add a deadline in your task, they will appear in the calendar
|
||||
view. As a manager, this view enables you to keep an eye on all
|
||||
deadlines in a single window.
|
||||
|
||||
.. image:: media/assignments10.png
|
||||
:align: center
|
||||
|
||||
All the tasks are tagged with a color corresponding to the employee
|
||||
assigned to them. You can easily filter the deadlines by employees by
|
||||
ticking the related boxes on the right of the calendar view.
|
||||
|
||||
.. tip::
|
||||
You can easily change the deadline from the Calendar view by
|
||||
dragging and dropping the task to another case.
|
||||
|
||||
.. seealso::
|
||||
* :doc:`../configuration/setup`
|
||||
* :doc:`forecast`
|
BIN
project/planning/media/assignments01.png
Normal file
After Width: | Height: | Size: 6.6 KiB |
BIN
project/planning/media/assignments02.png
Normal file
After Width: | Height: | Size: 18 KiB |
BIN
project/planning/media/assignments03.png
Normal file
After Width: | Height: | Size: 6.9 KiB |
BIN
project/planning/media/assignments04.png
Normal file
After Width: | Height: | Size: 50 KiB |
BIN
project/planning/media/assignments06.png
Normal file
After Width: | Height: | Size: 11 KiB |
BIN
project/planning/media/assignments07.png
Normal file
After Width: | Height: | Size: 18 KiB |
BIN
project/planning/media/assignments08.png
Normal file
After Width: | Height: | Size: 38 KiB |
BIN
project/planning/media/assignments09.png
Normal file
After Width: | Height: | Size: 16 KiB |
BIN
project/planning/media/assignments10.png
Normal file
After Width: | Height: | Size: 26 KiB |