Resupply subcontracting lead times
|
||||
==================================
|
||||
|
||||
.. |PO| replace:: :abbr:`PO (Purchase Order)`
|
||||
.. |RfQ| replace:: :abbr:`RfQ (Request for Quotation)`
|
||||
.. |BoM| replace:: :abbr:`BoM (Bill of Materials)`
|
||||
|
||||
In Odoo, lead times are used to predict how long it takes to complete a certain action. For example,
|
||||
a *delivery lead time* can be set for a purchased product, which specifies the number of days it
|
||||
usually takes for the product's vendor to deliver the product to the purchasing company.
|
||||
|
||||
For subcontracted products specifically, delivery lead times can be configured to take into account
|
||||
the amount of time required for the subcontractor to manufacture a product. Doing so allows the
|
||||
contracting company to better predict the delivery dates of subcontracted products.
|
||||
|
||||
Certain subcontracted products require the contracting company to supply the subcontractor with
|
||||
manufacturing components. In this case, a *manufacturing lead time* can be used, in addition to the
|
||||
delivery lead time, to generate the date on which the subcontractor must receive the required
|
||||
components, in order to manufacture the product and deliver it on time.
|
||||
|
||||
.. important::
|
||||
Like all lead times in Odoo, lead times for subcontracted products are only an estimate, and are
|
||||
based on how long actions are *expected* to take.
|
||||
|
||||
Unforeseen circumstances can impact the completion of these actions, which means that lead times
|
||||
should **not** be viewed as guarantees.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
When using the :doc:`Resupply Subcontractor on Order <subcontracting_resupply>` route, a company is
|
||||
responsible for supplying the subcontractor with the necessary components. As a result, the
|
||||
subcontractor cannot begin manufacturing until the components have been received.
|
||||
|
||||
This means that, in addition to the amount of time it takes the subcontractor to manufacture and
|
||||
deliver the product, the date they receive the components must also be considered.
|
||||
|
||||
By assigning a product's subcontractor a delivery lead time, and specifying a manufacturing lead
|
||||
time on the product's bill of materials (BoM), *Resupply Subcontractor* orders for the product's
|
||||
components display the deadline by which the subcontractor must receive the components.
|
||||
|
||||
Product delivery lead time
|
||||
--------------------------
|
||||
|
||||
To set a delivery lead time for a product's subcontractor, navigate to :menuselection:`Inventory app
|
||||
--> Products --> Products`, and select a subcontracted product.
|
||||
|
||||
Then, select the :guilabel:`Purchase` tab on the product's page. If the subcontractor has not
|
||||
already been added as a vendor, do so now by clicking :guilabel:`Add a line`, and selecting the
|
||||
subcontractor in the :guilabel:`Vendor` field.
|
||||
|
||||
Once the subcontractor has been added, enter the number of days it takes them to manufacture and
|
||||
deliver the product, in the :guilabel:`Delivery Lead Time` column.
|
||||
|
||||
.. image:: resupply_subcontracting_lead_times/delivery-lead-time.png
|
||||
:align: center
|
||||
:alt: The Delivery Lead Time field for a subcontractor, on the Purchase tab of a product page.
|
||||
|
||||
Product manufacturing lead time
|
||||
-------------------------------
|
||||
|
||||
Next, navigate to the product's |BoM| by clicking the :guilabel:`Bill of Materials` smart button at
|
||||
the top of the product's page. Then, select a |BoM| from the list.
|
||||
|
||||
On the |BoM|, select the :guilabel:`Miscellaneous` tab. In the :guilabel:`Manuf. Lead Time` field,
|
||||
enter the same number of days that was entered in the :guilabel:`Delivery Lead Time` field of the
|
||||
|BoM|'s product.
|
||||
|
||||
.. image:: resupply_subcontracting_lead_times/manufacturing-lead-time.png
|
||||
:align: center
|
||||
:alt: The Manuf. Lead Time field on a product's BoM.
|
||||
|
||||
While not all of these days are actually used for manufacturing by the subcontractor, setting the
|
||||
same number of days in each field tells Odoo that the subcontractor must receive the components and
|
||||
begin production by the start of the product's delivery lead time. This gives the subcontractor
|
||||
enough time to both manufacture and deliver the product.
|
||||
|
||||
Resupply subcontracting workflow
|
||||
--------------------------------
|
||||
|
||||
Create a request for quotation (RfQ) for the product by navigating to :menuselection:`Purchase app
|
||||
--> Orders --> Requests for Quotation`, and clicking :guilabel:`New`.
|
||||
|
||||
Specify the subcontractor in :guilabel:`Vendor` field. Then, add the product in the
|
||||
:guilabel:`Products` tab by clicking :guilabel:`Add a product`, selecting the product in the
|
||||
:guilabel:`Product` column, and specifying a quantity in the :guilabel:`Quantity` column.
|
||||
|
||||
In the :guilabel:`Expected Arrival` field, enter a date that provides enough time for the
|
||||
subcontractor to receive the components, manufacture the product, and deliver it back to the
|
||||
subcontracting company.
|
||||
|
||||
.. important::
|
||||
When a product is added to an |RfQ|, the :guilabel:`Expected Arrival` field auto-populates with a
|
||||
date that is today's date plus the delivery lead time of the product. However, this does **not**
|
||||
consider the time it takes to ship the components to the subcontractor.
|
||||
|
||||
When purchasing a product subcontracted using the Resupply Subcontractor on Order route, it is
|
||||
necessary to adjust this date to take into account the extra time needed for the components to be
|
||||
shipped to the subcontractor.
|
||||
|
||||
Since production does not begin until they receive the components, leaving the date as is results
|
||||
in the finished product arriving *after* the date listed on the |RfQ|.
|
||||
|
||||
Next, click :guilabel:`Confirm Order` to turn the |RfQ| into a |PO|. Doing so causes a
|
||||
:guilabel:`Resupply` smart button to appear at the top of the page.
|
||||
|
||||
Click the :guilabel:`Resupply` smart button to open the resupply subcontractor order, which is the
|
||||
order created to send components to the subcontractor.
|
||||
|
||||
The :guilabel:`Deadline` field on the resupply subcontractor order shows the deadline for the
|
||||
subcontractor to receive the components, in order for them to have enough time to manufacture and
|
||||
deliver the finished product by the Expected Arrival date.
|
||||
|
||||
The :guilabel:`Scheduled Date` field should display the latest date on which components can be
|
||||
shipped, while still arriving to the subcontractor by the :guilabel:`Deadline`. However, by default,
|
||||
the date displayed is the same as the date in the :guilabel:`Deadline` field, and must be updated to
|
||||
take into account the time required for shipping.
|
||||
|
||||
Click on the :guilabel:`Scheduled Date` field to open a calendar popover from which a date can be
|
||||
selected. Select a date that allows for the components to be delivered by the :guilabel:`Deadline`
|
||||
on the resupply subcontractor order.
|
||||
|
||||
After the components are shipped, click the :guilabel:`Validate` button at the top of the order to
|
||||
confirm they have been sent to the subcontractor.
|
||||
|
||||
Once the subcontractor receives the components, they begin manufacturing the component, before
|
||||
delivering it to the contracting company.
|
||||
|
||||
.. example::
|
||||
Bike retailer *Mike's Bikes* works with a subcontractor — *Bike Friends* — to produce units of
|
||||
their *Unicycle* product.
|
||||
|
||||
Mike's Bikes must supply Bike Friends with the necessary components for manufacturing the
|
||||
unicycles.
|
||||
|
||||
On average, Bike Friends takes three days to manufacture each unicycle, plus an additional two
|
||||
days to deliver it to Mike's Bikes.
|
||||
|
||||
As a result, Mike's Bikes sets a delivery lead time of five days for unicycles manufactured by
|
||||
Bike Friends: three days for manufacturing, plus two days for delivery.
|
||||
|
||||
On the unicycle's |BoM|, they enter a manufacturing lead time of five days, as well, to remind
|
||||
themselves of the date that components must be delivered to the subcontractor.
|
||||
|
||||
They confirm a |PO| for one unicycle, with an expected arrival date of May 30th.
|
||||
|
||||
The resupply subcontractor order for shipping the components to the subcontractor shows a
|
||||
*Deadline* of May 25th. The subcontractor must receive the components by this date, in order to
|
||||
have enough time to manufacture the unicycle, and deliver it by May 30th.
|
||||
|
||||
It takes Mike's Bikes two days to deliver the components, so they update the *Scheduled Date*
|
||||
field on the resupply subcontractor order to May 23rd, two days before the Deadline.
|
||||
|
||||
.. image:: resupply_subcontracting_lead_times/scheduled-deadline.png
|
||||
:align: center
|
||||
:alt: The Scheduled Date and Deadline fields on a resupply subcontractor order.
|
||||
|
||||
Mike's Bikes ships the components to Bike Friends on the scheduled date of May 23rd, and they
|
||||
arrive on the deadline of May 25th. This gives Bike Friends enough time to manufacture the
|
||||
unicycle, and ship it back to Mike's Bikes by the expected arrival date of May 30th.
|
Binary file not shown.
After Width: | Height: | Size: 11 KiB |
Binary file not shown.
After Width: | Height: | Size: 22 KiB |
Binary file not shown.
After Width: | Height: | Size: 22 KiB |
Loading…
Reference in New Issue
Block a user