[ADD] Manufacturing: Basic subcontracting lead times
closes odoo/documentation#9519
X-original-commit: 36da7b90a4
Signed-off-by: John Holton (hojo) <hojo@odoo.com>
This commit is contained in:
parent
93e76fe08b
commit
f83fce2125
@ -126,9 +126,9 @@ variables. For example, if the product is not dropshipped to the end customer, t
|
||||
to factor in the cost of dropshipping.
|
||||
|
||||
.. toctree::
|
||||
:titlesonly:
|
||||
|
||||
subcontracting/subcontracting_basic
|
||||
subcontracting/basic_subcontracting_lead_times
|
||||
subcontracting/subcontracting_resupply
|
||||
subcontracting/resupply_subcontracting_lead_times
|
||||
subcontracting/subcontracting_dropship
|
||||
|
@ -0,0 +1,101 @@
|
||||
===============================
|
||||
Basic subcontracting lead times
|
||||
===============================
|
||||
|
||||
.. |PO| replace:: :abbr:`PO (Purchase Order)`
|
||||
.. |RfQ| replace:: :abbr:`RfQ (Request for Quotation)`
|
||||
|
||||
In Odoo, lead times are used to predict how long it takes to complete a certain action. For example,
|
||||
a *delivery lead time* can be set for a purchased product, which specifies the number of days it
|
||||
usually takes for the product's vendor to delivery the product to the purchasing company.
|
||||
|
||||
For subcontracted products specifically, delivery lead times can be configured to take into account
|
||||
the amount of time required for the subcontractor to manufacture a product. Doing so allows the
|
||||
contracting company to better predict the delivery dates of subcontracted products.
|
||||
|
||||
.. important::
|
||||
Like all lead times in Odoo, lead times for subcontracted products are only an estimate, and are
|
||||
based on how long actions are *expected* to take.
|
||||
|
||||
Unforeseen circumstances can impact the completion of these actions, which means that lead times
|
||||
should not be viewed as guarantees.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
When using the :doc:`basic subcontracting <subcontracting_basic>` workflow to manufacture a product,
|
||||
a company is not responsible for supplying the subcontractor with the necessary components. This
|
||||
means that the only factors affecting the delivery date of a product are the amount of time it takes
|
||||
the subcontractor to manufacture and deliver it.
|
||||
|
||||
By assigning a product's subcontractor a delivery lead time that considers both of these factors,
|
||||
the *Expected Arrival* date displayed on purchase orders (POs) for the product more accurately
|
||||
reflects the amount of time required for both manufacturing and delivery.
|
||||
|
||||
Product delivery lead time
|
||||
--------------------------
|
||||
|
||||
To set a delivery lead time for a product's subcontractor, navigate to :menuselection:`Inventory app
|
||||
--> Products --> Products`, and select a subcontracted product.
|
||||
|
||||
Then, select the :guilabel:`Purchase` tab on the product's page. If the subcontractor has not
|
||||
already been added as a vendor, do so now by clicking :guilabel:`Add a line`, and selecting the
|
||||
subcontractor in the :guilabel:`Vendor` column.
|
||||
|
||||
Once the subcontractor has been added, enter the number of days it takes them to manufacture and
|
||||
deliver the product, in the :guilabel:`Delivery Lead Time` column.
|
||||
|
||||
.. image:: basic_subcontracting_lead_times/delivery-lead-time.png
|
||||
:align: center
|
||||
:alt: The Delivery Lead Time field for a subcontractor, on the Purchase tab of a product page.
|
||||
|
||||
.. note::
|
||||
Multiple subcontractors can be added to the :guilabel:`Purchase` tab on a product's page, and a
|
||||
different :guilabel:`Delivery Lead Time` can be set for each.
|
||||
|
||||
Lead time workflow
|
||||
==================
|
||||
|
||||
After setting a delivery lead time for a product's vendor, create an |RfQ| by navigating to
|
||||
:menuselection:`Purchase app --> Orders --> Purchase Orders`, and clicking :guilabel:`New`.
|
||||
|
||||
Specify the subcontractor in the :guilabel:`Vendor` field. Then, add the product in the
|
||||
:guilabel:`Products` tab by clicking :guilabel:`Add a product`, selecting the product in the
|
||||
:guilabel:`Product` column, and adding a quantity in the :guilabel:`Quantity` column.
|
||||
|
||||
Once a product has been added, the :guilabel:`Expected Arrival` field on the |RfQ| auto-populates
|
||||
with a date that reflects the vendor's delivery lead time, as specified on the product's page.
|
||||
|
||||
If the date needs to be adjusted, click on the :guilabel:`Expected Arrival` field to open a calendar
|
||||
popover, and select the desired date. Make sure not to choose a date sooner than the one that was
|
||||
auto-populated, unless the subcontractor has confirmed that they are able to deliver the product by
|
||||
that date.
|
||||
|
||||
Finally, click :guilabel:`Confirm Order` on the |RfQ| to turn it into a |PO|. At this point, the
|
||||
subcontractor should begin manufacturing the subcontracted product, before delivering it to the
|
||||
contracting company.
|
||||
|
||||
.. example::
|
||||
Bike retailer *Mike's Bikes* works with a subcontractor — *Bike Friends* — to produce units of
|
||||
their *Tricycle* product.
|
||||
|
||||
On average, Bike Friends requires three days to manufacture a tricycle, plus an additional two
|
||||
days to deliver it to Mike's Bikes.
|
||||
|
||||
As a result, Mike's Bikes sets a delivery lead time of five days for tricycles manufactured by
|
||||
Bike Friends: three days for manufacturing, plus two days for delivery.
|
||||
|
||||
On May 3rd, Mike's Bikes confirms a |PO| to purchase one tricycle from Bike Friends.
|
||||
|
||||
The :guilabel:`Expected Arrival` date listed on the |PO| is May 8th, five days after the
|
||||
:guilabel:`Confirmation Date`.
|
||||
|
||||
.. image:: basic_subcontracting_lead_times/expected-arrival.png
|
||||
:align: center
|
||||
:alt: The Expected Arrival date on a PO for a subcontracted product.
|
||||
|
||||
Bike Friends begins manufacturing the tricycle on May 3rd — the day that the |PO| is confirmed —
|
||||
and finishes on May 6th, three days later.
|
||||
|
||||
The tricycle is then shipped to Mike's Bikes the same day, and they receive it on May 8th, two
|
||||
days later.
|