How is the scheduled delivery date computed?
|
|
============================================
|
|
|
|
Scheduled dates are computed in order to be able to plan deliveries,
|
|
receptions and so on. Depending on the habits of your company Odoo
|
|
automatically generates scheduled dates via the scheduler. The Odoo
|
|
scheduler computes everything per line, whether it's a manufacturing
|
|
order, a delivery order, a sale order, etc. The dates that are computed
|
|
are dependent on the different leads times configured in Odoo.
|
|
|
|
Configuring lead times
|
|
======================
|
|
|
|
Configuring **lead times** is a first essentiel move in order to compute
|
|
scheduled dates. Lead times are the delays (in term of delivery,
|
|
manufacturing, ...) promised to your different partners and/or clients.
|
|
|
|
Configuration of the different lead times are made as follows:
|
|
|
|
At a product level
|
|
------------------
|
|
|
|
- **Supplier lead time**:
|
|
|
|
Is the time needed for the supplier to deliver your purchased product.
|
|
To configure the supplier lead time select a product, and go in the
|
|
**Inventory** tab. You will have to add a vendor to your product in order
|
|
to select a supplier lead time.
|
|
|
|
.. image:: media/scheduled_dates05.png
|
|
:align: center
|
|
|
|
.. tip::
|
|
Do not forget that it is possible to add different vendors and thus
|
|
different delivery lead times depending on the vendor.
|
|
|
|
Once a vendor is selected, just open its form and fill its **Delivery lead
|
|
time**. In this case security days have no influence, the scheduled
|
|
delivery days will be equal to: **Date** of the purchase order + **Delivery
|
|
Lead Time**.
|
|
|
|
.. image:: media/scheduled_dates02.png
|
|
:align: center
|
|
|
|
- **Customer lead time**:
|
|
|
|
Customer lead time is the time needed to get your product from your
|
|
store / warehouse to your customer. It can be configured for any
|
|
product. Simply select a product, go into the sales tab and indicate
|
|
your **Customer lead time**.
|
|
|
|
.. image:: media/scheduled_dates01.png
|
|
:align: center
|
|
|
|
- **Manufacturing lead time**:
|
|
|
|
At the same page it is possible to configure the **Manufacturing Lead
|
|
Time** as well. Manufacturing lead time is the time needed to
|
|
manufacture the product.
|
|
|
|
.. tip::
|
|
Don't forget to tick the manufacturing box in inventory if you
|
|
want to create manufacturing routes.
|
|
|
|
At the company level
|
|
--------------------
|
|
|
|
At company level, it is possible to configure **security days** in order
|
|
to cope with eventual delays and to be sure to meet your engagements.
|
|
The idea is to subtract **backup** days from the **computed scheduled date**
|
|
in case of delays.
|
|
|
|
- **Sales Safety days**:
|
|
|
|
Sales safety days are **back-up** days to ensure you will be able to
|
|
deliver your clients engagements in times. They are margins of errors
|
|
for delivery lead times. Security days are the same logic as the early
|
|
wristwatch, in order to arrive on time. The idea is to subtract the
|
|
numbers of security days from the calculation and thus to compute a
|
|
scheduled date earlier than the one you promised to your client. In that
|
|
way you are sure to be able to keep your commitment.
|
|
|
|
To set ut your security dates, go to :menuselection:`Settings --> General settings` and
|
|
click on **Configure your company data**.
|
|
|
|
.. image:: media/scheduled_dates04.png
|
|
:align: center
|
|
|
|
Once the menu is open, go in the configuration tab and indicate the
|
|
number of safety days.
|
|
|
|
- **Purchase Safety days**:
|
|
|
|
Purchase days follow to the same logic than sales security days.
|
|
|
|
They are margins of error for vendor lead times. When the system
|
|
generates purchase orders for procuring products, they will be scheduled
|
|
that many days earlier to cope with unexpected vendor delays. Purchase
|
|
lead time can be found in the same menu as the sales safety days
|
|
|
|
.. image:: media/scheduled_dates03.png
|
|
:align: center
|
|
|
|
.. tip::
|
|
Note that you can also configure a default
|
|
Manufacturing lead time from here.
|
|
|
|
At route level
|
|
--------------
|
|
|
|
The internal transfers that a product might do due to the movement of
|
|
stocks can also influence the computed date.
|
|
|
|
The delays due to internal transfers can be specified in the **inventory**
|
|
app when creating a new push rule in a route.
|
|
|
|
Go to the push rules section on a route form to set a delay.
|
|
|
|
.. image:: media/scheduled_dates06.png
|
|
:align: center
|
|
|
|
At sale order level:
|
|
--------------------
|
|
|
|
- **Requested date**:
|
|
|
|
Odoo offers the possibility to select a requested date by the client by
|
|
indicating the date in the other information tab of the sales order.
|
|
If this date is earlier than the theoreticaly computed date odoo will
|
|
automatically display a warning.
|
|
|
|
.. image:: media/scheduled_dates07.png
|
|
:align: center
|
|
|
|
Example
|
|
=======
|
|
|
|
As an example, you may sell a car today (January 1st), that is purchased
|
|
on order, and you promise to deliver your customer within 20 days
|
|
(January 20). In such a scenario, the scheduler may trigger the
|
|
following events, based on your configuration:
|
|
|
|
- January 19: actual scheduled delivery (1 day of Sales Safety days)
|
|
|
|
- January 18: receive the product from your supplier (1 day of Purchase
|
|
days)
|
|
|
|
- January 10: deadline to order at your supplier (9 days of supplier
|
|
delivery lead time)
|
|
|
|
- January 8: trigger a purchase request to your purchase team, since
|
|
the team need on average 2 days to find the right supplier and
|
|
order.
|