Task dependencies
=================
Odoo Project allows you to break down projects into tasks and establish relationships between those
tasks to determine the order in which they are executed. Task dependencies ensure that certain tasks
begin only after the preceding tasks are completed.
To enable task dependencies in Projects, go to :menuselection:`Project --> Configuration -->
Settings`, enable :guilabel:`Task Dependencies`, and click the :icon:`fa-cloud-upload`
(:guilabel:`save`) icon.
Set task dependencies
=====================
Task dependencies can be created from the task form or the project's Gantt view by linking the
successor task (i.e., the task blocked by other tasks) to its predecessor task(s) (i.e., the tasks
blocking the successor task).
To create task dependencies from the task form, access the desired task and, in the
:guilabel:`:guilabel:`Blocked by` tab, click :guilabel:`Add a line`. To access successor tasks from
the predecessor task, click the :guilabel:`Blocking Tasks` smart button.
To create a task dependency from the Gantt view, hover your mouse over the predecessor task, then
click one of the dots that appear around it. Drag and drop the dot onto the successor task. An arrow
will appear, indicating the dependency from the predecessor task to the successor.
.. image:: task_dependencies/task-dependency.png
:alt: Task dependency
Odoo automatically manages task progress based on their dependency. Successor tasks are assigned the
:guilabel:`Waiting` status and cannot be moved to :guilabel:`In Progress` until their predecessor
task(s) are marked as :guilabel:`Approved`, :guilabel:`Cancelled` or :guilabel:`Done`.
Remove dependencies
===================
- From the task form: go to the **Blocked by** tab and click the :icon:`fa-times` button.
- From Gantt view: click the red :guilabel:`X` button that appears at the center of the arrow when
you hover your mouse over it.