How are the order date and scheduled dates computed?
|
||||
====================================================
|
||||
====================================================
|
||||
|
||||
Scheduled dates are computed in order to be able to plan deliveries,
|
||||
receptions and so on. Depending on the habits of your company, Odoo
|
||||
automatically generates scheduled dates via the scheduler. The Odoo
|
||||
scheduler computes everything per line, whether it's a manufacturing
|
||||
order, a delivery order, a sale order, etc. The dates that are computed
|
||||
are dependent on the different leads times configured in Odoo.
|
||||
|
||||
Configuring lead times
|
||||
======================
|
||||
|
||||
Configuring **lead times** is an essential move in order to compute
|
||||
scheduled dates. Lead times are the delays (in term of delivery,
|
||||
manufacturing, ...) promised to your different partners and/or clients.
|
||||
Configuration of the different lead times are made as follows:
|
||||
|
||||
On a product level
|
||||
------------------
|
||||
|
||||
Supplier lead time:
|
||||
~~~~~~~~~~~~~~~~~~~
|
||||
|
||||
The supplier lead time is the time needed for the supplier to deliver
|
||||
your purchased product. To configure the Supplier lead time select a
|
||||
product (from the Purchase module, go to :menuselection:`Purchase --> Product`),
|
||||
and go in the **Inventory** tab. You will have to
|
||||
add a **Vendor** to your product in order to select a supplier lead time.
|
||||
|
||||
.. image:: media/compute_date01.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
It is possible to add more than one vendor per product and thus
|
||||
different delivery lead times depending on the vendor.
|
||||
|
||||
Once a vendor is selected, click on it to open its form and indicate its
|
||||
delivery lead time.
|
||||
|
||||
.. image:: media/compute_date02.png
|
||||
:align: center
|
||||
|
||||
.. note::
|
||||
In this case security days have no influence, the scheduled
|
||||
delivery days will be equal to: Date of the purchase order + Delivery Lead Time.
|
||||
|
||||
Customer lead time
|
||||
~~~~~~~~~~~~~~~~~~
|
||||
|
||||
The customer lead time is the time needed to get your product from your
|
||||
store/warehouse to your customer. It can be configured for any
|
||||
product. Simply select a product (from the **Sales** module, go to
|
||||
:menuselection:`Sales --> Product`),
|
||||
and go into the **Sales** tab to indicate your customer lead time.
|
||||
|
||||
.. image:: media/compute_date03.png
|
||||
:align: center
|
||||
|
||||
On the company level
|
||||
--------------------
|
||||
|
||||
On company level, it is possible to parameter **security days** in order
|
||||
to cope with eventual delays and to be sure to meet your engagements.
|
||||
The idea is to subtract **backup** days from the computed scheduled date
|
||||
in case of delays.
|
||||
|
||||
Sales Safety days
|
||||
~~~~~~~~~~~~~~~~~
|
||||
|
||||
Sales Safety days are **back-up** days to ensure you will be able to
|
||||
deliver your clients engagements on time. They are margins of errors for
|
||||
delivery lead times. Security days are the same logic as the early
|
||||
wristwatch, in order to arrive on time. The idea is to subtract the
|
||||
numbers of security days from the calculation and thus to compute a
|
||||
scheduled date earlier than the one you promised to your client. That
|
||||
way you are sure to be able to keep your commitment.
|
||||
|
||||
To set up your security dates, go to the app
|
||||
:menuselection:`Settings --> General settings`,
|
||||
and click on **Configure your company data**.
|
||||
|
||||
.. image:: media/compute_date04.png
|
||||
:align: center
|
||||
|
||||
Go the **Configuration** tab to indicate the number of safety days
|
||||
|
||||
.. image:: media/compute_date05.png
|
||||
:align: center
|
||||
|
||||
.. tip::
|
||||
Note that you can in this menu configure
|
||||
a default **Manufacturing** lead time.
|
||||
|
||||
Purchase days
|
||||
~~~~~~~~~~~~~
|
||||
|
||||
Purchase days response to the same logic than sales security days.
|
||||
|
||||
They are margins of error for vendor lead times. When the system
|
||||
generates purchase orders for procuring products, they will be scheduled
|
||||
in order to cope with unexpected vendor delays. Purchase lead time can
|
||||
be found in the same menu as the sales safety days (see screenshot
|
||||
above).
|
||||
|
||||
On route level
|
||||
--------------
|
||||
|
||||
The internal transfers due to the movement of stocks can also influence
|
||||
the computed date.
|
||||
|
||||
The delays due to internal transfers can be specified in the **Inventory**
|
||||
module when creating a new push rule for a new route.
|
||||
|
||||
.. note::
|
||||
Read the documentation
|
||||
:doc:`../../../../inventory/routes/concepts/push_rule`
|
||||
to learn more.
|
||||
|
||||
.. image:: media/compute_date06.png
|
||||
:align: center
|
||||
|
||||
On document level:
|
||||
------------------
|
||||
|
||||
Requested date
|
||||
~~~~~~~~~~~~~~
|
||||
|
||||
Odoo offers the possibility to indicate a requested date by the client
|
||||
straight on the sale order, under the tab **Other information**. If
|
||||
this date is earlier than the theoretically computed date, Odoo will
|
||||
automatically display a warning.
|
||||
|
||||
.. image:: media/compute_date07.png
|
||||
:align: center
|
||||
|
||||
Example
|
||||
=======
|
||||
|
||||
As an example, you may sell a car today (January 1st), that is purchased
|
||||
on order, and you promise to deliver your customer within 20 days
|
||||
(January 20). In such a scenario, the scheduler may trigger the
|
||||
following events, based on your configuration:
|
||||
|
||||
- January 19: actual scheduled delivery (1 day of Sales Safety days)
|
||||
|
||||
- January 18: receive the product from your supplier (1 day of Purchase
|
||||
days)
|
||||
|
||||
- January 10: deadline to order at your supplier (9 days of supplier
|
||||
delivery lead time)
|
||||
|
||||
- January 8: trigger a purchase request to your purchase team, since
|
||||
the team needs on average 2 days to find the right supplier and
|
||||
order.
|
||||
|
BIN
purchase/replenishment/flows/media/compute_date01.png
Normal file
After Width: | Height: | Size: 19 KiB |
BIN
purchase/replenishment/flows/media/compute_date02.png
Normal file
After Width: | Height: | Size: 12 KiB |
BIN
purchase/replenishment/flows/media/compute_date03.png
Normal file
After Width: | Height: | Size: 16 KiB |
BIN
purchase/replenishment/flows/media/compute_date04.png
Normal file
After Width: | Height: | Size: 10 KiB |
BIN
purchase/replenishment/flows/media/compute_date05.png
Normal file
After Width: | Height: | Size: 21 KiB |
BIN
purchase/replenishment/flows/media/compute_date06.png
Normal file
After Width: | Height: | Size: 12 KiB |
BIN
purchase/replenishment/flows/media/compute_date07.png
Normal file
After Width: | Height: | Size: 20 KiB |