[FIX] inventory_and_mrp: documentation update

After this PR: https://github.com/odoo/odoo/pull/78199

The explanation of the `Security Lead Time for Purchase` field needs to be updated

opw-2766940

closes odoo/documentation#1841

X-original-commit: 9c242400b6
Signed-off-by: Antoine Vandevenne (anv) <anv@odoo.com>
Signed-off-by: Djamel Touati (otd) <otd@odoo.com>
This commit is contained in:
Touati Djamel (otd) 2022-04-05 14:43:01 +00:00
parent 27e9c1b2f2
commit 84ecfaa4a8
2 changed files with 5 additions and 7 deletions

View File

@ -38,12 +38,10 @@ are:
customer. Then, the default scheduled date on the delivery order
is **SO delivery date - Security Lead Time**.
- **Purchase Security Lead Time**: additional time to mitigate the risk
of a vendor delay. The receipt will be scheduled that many days
earlier to cope with unexpected vendor delays. In case of a
*Replenish to Order*, the **Delivery order scheduled date -
Security lead time** for purchase will be the default
*Receipt* scheduled date.
- **Purchase Security Lead Time**: margin of error for vendor lead times.
When the system generates Purchase Orders for procuring products,
they will be scheduled that many days earlier to cope with unexpected
vendor delays.
- **Purchase Delivery Lead Time**: this is the expected time between a
PO being confirmed and the receipt of the ordered products. The

View File

@ -1516,7 +1516,7 @@ msgid "**Sales Security Lead Time**: the purpose is to be ready shipping that ma
msgstr ""
#: ../../content/applications/inventory_and_mrp/inventory/management/planning/scheduled_dates.rst:41
msgid "**Purchase Security Lead Time**: additional time to mitigate the risk of a vendor delay. The receipt will be scheduled that many days earlier to cope with unexpected vendor delays. In case of a *Replenish to Order*, the **Delivery order scheduled date - Security lead time** for purchase will be the default *Receipt* scheduled date."
msgid "**Purchase Security Lead Time**: Margin of error for vendor lead times. When the system generates Purchase Orders for procuring products, they will be scheduled that many days earlier to cope with unexpected vendor delays."
msgstr ""
#: ../../content/applications/inventory_and_mrp/inventory/management/planning/scheduled_dates.rst:48