@ -2,6 +2,10 @@
|
|||||||
Scheduled delivery dates
|
Scheduled delivery dates
|
||||||
========================
|
========================
|
||||||
|
|
||||||
|
.. |MOs| replace:: :abbr:`MOs (Manufacturing Orders)`
|
||||||
|
.. |BoM| replace:: :abbr:`BoM (Bill of Materials)`
|
||||||
|
.. |BoMs| replace:: :abbr:`BoMs (Bills of Materials)`
|
||||||
|
|
||||||
Accurately forecasting delivery dates is vital for fulfilling customer expectations. In Odoo, the
|
Accurately forecasting delivery dates is vital for fulfilling customer expectations. In Odoo, the
|
||||||
*Inventory* app allows for comprehensive lead time configuration, allowing coordination and planning
|
*Inventory* app allows for comprehensive lead time configuration, allowing coordination and planning
|
||||||
of manufacturing orders, deliveries, and receptions.
|
of manufacturing orders, deliveries, and receptions.
|
||||||
@ -233,7 +237,7 @@ Manufacturing lead times
|
|||||||
========================
|
========================
|
||||||
|
|
||||||
Lead times can help simplify the procurement process for consumable materials and components used in
|
Lead times can help simplify the procurement process for consumable materials and components used in
|
||||||
manufactured products with bills of materials.
|
manufactured products with bills of materials (BoMs).
|
||||||
|
|
||||||
The :abbr:`MO (Manufacturing Order)` deadline, which is the deadline to begin the manufacturing
|
The :abbr:`MO (Manufacturing Order)` deadline, which is the deadline to begin the manufacturing
|
||||||
process to complete the product by the scheduled delivery date, can be determined by configuring the
|
process to complete the product by the scheduled delivery date, can be determined by configuring the
|
||||||
@ -246,19 +250,35 @@ manufacturing lead times and manufacturing security lead times.
|
|||||||
Manufacturing lead time
|
Manufacturing lead time
|
||||||
-----------------------
|
-----------------------
|
||||||
|
|
||||||
Configure the manufacturing lead time directly on the product form, by navigating to
|
Manufacturing lead times for products are configured from a product's bill of materials (BoM) form.
|
||||||
:menuselection:`Manufacturing app --> Products --> Products`, and select the desired product.
|
|
||||||
|
|
||||||
In the :guilabel:`Inventory` tab of the product, specify the calendar days needed to the manufacture
|
To add a lead time to a |BoM|, navigate to :menuselection:`Manufacturing app --> Products --> Bills
|
||||||
the product in the :guilabel:`Manufacturing Lead Time` field.
|
of Materials`, and select the desired |BoM| to edit.
|
||||||
|
|
||||||
.. example::
|
On the |BoM| form, click the :guilabel:`Miscellaneous` tab. Change the value (in days) in the
|
||||||
Specify a 14-day :guilabel:`Manufacturing Lead Time` for a product directly in the
|
:guilabel:`Manuf. Lead Time` field to specify the calendar days needed to manufacture the product.
|
||||||
:guilabel:`Inventory` tab of the product.
|
|
||||||
|
|
||||||
.. image:: scheduled_dates/set-manufacturing.png
|
.. image:: scheduled_dates/scheduled-dates-manuf-lead-time.png
|
||||||
:align: center
|
:align: center
|
||||||
:alt: View of the manufacturing lead time configuration from the product form.
|
:alt: Manuf. Lead Time value specified on a product's Bill of Material form.
|
||||||
|
|
||||||
|
.. note::
|
||||||
|
If the selected |BoM| is a multi-level |BoM|, the manufacturing lead times of the components are
|
||||||
|
added.
|
||||||
|
|
||||||
|
If the |BoM| product is subcontracted, the :guilabel:`Manuf. Lead Time` can be used to determine
|
||||||
|
the date at which components should be sent to the subcontractor.
|
||||||
|
|
||||||
|
Change the value (in days) in the :guilabel:`Days to prepare Manufacturing Order` field to create
|
||||||
|
and confirm |MOs| in advance, and have enough time to replenish components, or manufacture
|
||||||
|
semi-finished products.
|
||||||
|
|
||||||
|
.. tip::
|
||||||
|
Clicking :guilabel:`Compute`, located next to the :guilabel:`Days to prepare Manufacturing Order`
|
||||||
|
field, computes the days required to resupply all components listed on the |BoM| form, either by
|
||||||
|
buying or manufacturing the components or subassemblies.
|
||||||
|
|
||||||
|
*Purchase security lead times* that impact this specific |BoM| are also added to this value.
|
||||||
|
|
||||||
Establish a :abbr:`MO (Manufacturing Order)` deadline, based on the *expected delivery date*,
|
Establish a :abbr:`MO (Manufacturing Order)` deadline, based on the *expected delivery date*,
|
||||||
indicated in the :guilabel:`Scheduled Date` field of the :abbr:`DO (Delivery Order)`.
|
indicated in the :guilabel:`Scheduled Date` field of the :abbr:`DO (Delivery Order)`.
|
||||||
|