# Project dashboard
|
||
|
||
The project dashboard allows you to get a comprehensive overview of your project's status. It
|
||
displays information such as the total number of tasks, timesheets, and planned hours linked to the
|
||
project, as well as detailed information about project milestones and its costs and revenues. Within
|
||
the project dashboard, you can create {guilabel}`Project updates`, which allow you to take a
|
||
snapshot of the project's status at a certain point in time. As such, it is a crucial tool for
|
||
effective project management and ensuring that your project stays on track.
|
||
|
||
## Using the project dashboard
|
||
|
||
To access the project dashboard, open the **Project** app and hover over the desired project’s
|
||
card. Then, click the {icon}`fa-vertical-ellipsis` ({guilabel}`vertical ellipsis`) icon and
|
||
select {guilabel}`Dashboard`. Alternatively, you can access the project dashboard from the project’s
|
||
{ref}`top bar <project/project-management/top-bar>`.
|
||
|
||
The left side of the dashboard displays a list of existing {ref}`project updates <project/project-dashboard/updates>`,
|
||
and the right side provides {ref}`detailed information about records linked to the project
|
||
<project/project-dashboard/smart-buttons>`, as well as {ref}`milestones <project/project-dashboard/milestones>`,
|
||
{ref}`profitability <project/project-dashboard/profitability>`, and {ref}`budgets
|
||
<project/project-dashboard/budgets>`.
|
||
|
||
:::{note}
|
||
The information displayed on the project dashboard varies depending on the applications installed
|
||
on your database. For example, you will not see information about **Timesheets**, **Planning**,
|
||
or **Purchase Orders** if the corresponding applications are not installed.
|
||
:::
|
||
|
||
(project-project-dashboard-smart-buttons)=
|
||
|
||
### Totals smart buttons
|
||
|
||
The following smart buttons are displayed on the top right of the project dashboard:
|
||
|
||
> - {guilabel}`Tasks`: the number of completed (i.e., {guilabel}`Done` or {guilabel}`Canceled`
|
||
> {ref}`tasks <project/tasks/task_stages_statuses/statuses>`) and all tasks, in format
|
||
> completed/all, as well as the entire project's completion percentage estimation.
|
||
> - {guilabel}`Timesheets`: the number of hours or days (depending on the **Timesheets** app
|
||
> configuration) allocated in the project’s **settings**. This includes all
|
||
> {doc}`timesheets <../timesheets>`, whether or not they have been validated.
|
||
> - {guilabel}`Planned`: the number of hours that have been planned for shifts in the **Planning**
|
||
> app. This includes all {doc}`planned shifts <../planning>`, including past shifts and shifts that
|
||
> have not yet been published.
|
||
> - {guilabel}`Documents`: number of {doc}`documents <../../productivity/documents>` in the
|
||
> project’s workspace.
|
||
> - {guilabel}`Burndown Chart`: click the smart button to access a {doc}`report </applications/essentials/reporting>`
|
||
> on the status of the project’s tasks over time.
|
||
> - {guilabel}`Timesheets and Planning`: click the smart button to access a {doc}`report </applications/essentials/reporting>`
|
||
> on the project’s timesheets and shifts. This allows you to easily compare planned and effective
|
||
> hours of work on the project.
|
||
> - **Additional fields**, such as {guilabel}`Sales Orders`, {guilabel}`Sales Order Items`,
|
||
> {guilabel}`Purchase Orders`, and more, represent the number of records linked to the project.
|
||
|
||
:::{tip}
|
||
Use the project dashboard smart buttons to update the project records easily. Click
|
||
{guilabel}`Timesheets` to validate timesheets, {guilabel}`Planned` to create project planning,
|
||
{guilabel}`Documents` to view and validate documents, etc.
|
||
:::
|
||
|
||
(project-project-dashboard-milestones)=
|
||
|
||
### Milestones
|
||
|
||
This section is only visible if {doc}`milestones </applications/sales/sales/invoicing/milestone>`
|
||
have been enabled in the Project’s app settings. Click {guilabel}`Add Milestone` to create a new
|
||
milestone. Click a milestone in the checklist to edit it, enable its checkbox to mark it as
|
||
completed, or click the {icon}`fa-trash` ({guilabel}`trash`) icon to remove it.
|
||
|
||
The milestones are displayed in red if they’re past their deadline, or in green if they are ready to
|
||
be marked as reached (i.e. tasks linked to the milestone that have been marked with {guilabel}`done`
|
||
or {guilabel}`canceled` {ref}`status <project/tasks/task_stages_statuses/statuses>`).
|
||
|
||
(project-project-dashboard-profitability)=
|
||
|
||
### Profitability
|
||
|
||
This section provides a breakdown of project costs and revenues, which are impacted by all records
|
||
linked to the project and its {doc}`Analytic account </applications/finance/accounting/reporting/analytic_accounting>`.
|
||
|
||
:::{note}
|
||
The profitability report is only displayed for billable projects.
|
||
:::
|
||
|
||
(project-project-dashboard-budgets)=
|
||
|
||
### Budgets
|
||
|
||
If a budget has been set for the project, its status and related details are displayed in this
|
||
section. Click {guilabel}`Add Budget` to create a new budget for the project.
|
||
|
||
:::{note}
|
||
{doc}`Budgets </applications/finance/accounting/reporting/budget>` must be enabled in your
|
||
database’s **Accounting** application in order for this section to be displayed.
|
||
:::
|
||
|
||
(project-project-dashboard-updates)=
|
||
|
||
## Project updates
|
||
|
||
Project updates allow you to take a snapshot of the project’s overall status at a given point in
|
||
time, for example, during a periodic (weekly, bi-weekly, or monthly) review. This allows you to
|
||
compare specific data points, note any aspects of the project that need improvement, and estimate
|
||
if the project is on or off track.
|
||
|
||
To create a new project update, go to the project dashboard, click {guilabel}`New`, and fill in the
|
||
following fields:
|
||
|
||
> - {guilabel}`Status`: Choose between {guilabel}`On Track`, {guilabel}`At Risk`, {guilabel}`Off
|
||
> Track`, {guilabel}`On Hold`, and {guilabel}`Done`. Once the status is set, a color-coded dot is
|
||
> displayed on the project’s Kanban card, allowing the project manager to easily identify which
|
||
> projects need attention.
|
||
> - {guilabel}`Progress`: Manually input the completion percentage based on the project's progress.
|
||
> - {guilabel}`Date` and {guilabel}`Author`: These fields are automatically filled in with
|
||
> appropriate information based on the user who created the update and the current date.
|
||
> - {guilabel}`Description`: Use this rich-text field to gather notes. Depending on the project
|
||
> configuration (e.g., if the project is billable), this field may be pre-filled with current
|
||
> information on aspects such as profitability, budget, milestones, etc.
|
||
|